Aish Ha Torah
Meeting Challenges of Unusual Proportions
Today, places of worship of every size and denomination are challenging traditional building ideas and seeking creative ways to conduct ministry to reach out to the community. Gone are the days when attendance was solely at Sunday service. Instead, today's religious buildings are used throughout the week for various meetings, education, dining and recreational activities that reflect the growing needs of the congregation.
In meeting these challenges, churches have become conscious of the need to create flexible spaces that keep building costs down while providing a suitable environment for a variety of activities. Churches anticipating construction today include multipurpose rooms in their blueprints, while existing structures have the option to draw on simple conversion plans. Creative thought and a capable contractor are often all that is necessary to create flexible space without undertaking massive remodeling. A good example of this is the Aish Ha Torah Synagogue in West Los Angeles, California.
Miguel Escobar, Architect with Angelworks Architecture, designed the Aish Ha Torah Synagogue to serve a congregation of 2,000. It was decided that one of the large rooms should have doors capable of transforming it into two smaller rooms. When not in use, the doors were to be flush with the walls to conserve space and blend in with the overall architecture of the room. When the room needed to be divided, ease of operation was a necessary feature according to the owner.
Krieger constructed two swinging doors, each 22 ft. wide, 14 ft. high and 4 In. thick.
The Aish Ha Torah Synagogue serves a congregation of 2,000 in West Los Angeles, California.
Drawing on past experience in designing custom and oversized acoustical doors for such installations as the Lied Center in Lincoln, Nebraska, Krieger Specialty Products was selected to design and manufacture the doors in order to meet acoustical, aesthetic and engineering demands. The design was limited to mechanical operation only, without the use of any electrical or pneumatic power assistance or sealing devices.
The architectural design and sheer size of the 44 ft. wide, 14 ft. high room presented many challenges. Divider doors would have to span the entire width of the room, which meant they had to be engineered to avoid sag or deflection. Windows that lined both walls would have to provide natural light for both rooms. Door faces had to be flat with no ripples or indentations in order to accommodate a wood veneer finish. And, since it was expected that both rooms would be used simultaneously, acoustical control was also an issue to be addressed.
The acoustical requirement was to maintain an overall NRC 30 value for both rooms, so the design criteria established a required STC rating of 45 or higher.
When not in use the doors are flush with the walls to conserve space.
After some initial design experimentation, the Krieger team decided to construct two swinging doors, each 22 ft. wide, 14 ft. high and 4 In. thick. To accommodate shipping and passage into the room for actual assembly, the doors were split into three panels, 7 ft. x 14 ft. per door. To provide good acoustical design and strength, each panel was fabricated with a tubular "skeleton" made of 4 in. tube steel and 14-gauge cold rolled steel skins. Additionally, double-glazed windows on the doors were positioned to match the position of the windows on the outer walls, allowing natural light to pass through the doors whether they were flush with the wall or dividing the room.
Since the walls, ceilings and floors were already in place, installation became the final challenge. Using specially equipped forklifts; one outside the room and one inside the room, Krieger was able to safely maneuver the six massive panels, each weighing over 1,500 lbs. through a standard 3 ft. x 8 ft. door, the only usable access into the room.
Once inside, each panel was raised and aligned onto a pair of large, 40 lb. hinges specially made to support the 6,000 lbs. of each assembled door. Each panel was attached to steel beams built into the walls specifically for this purpose. After the first panel was lined up and installed, the other panels were installed using a "tongue & groove" joint that made each panel fit together. The panels were secured together using a heavy-duty drill and special hardened steel bolts, and sound gasketing was mounted at the perimeter of both doors.
A room of this size usually has some small degree of unleveling, but the painstaking work and determination of the installation crew met the 7/8 in. clearance of both the floors and ceilings.
The result is a unique and functional door solution that impresses with its size, beauty and mechanics and is perfectly suited for a structure dedicated to inspiring infinite human potential.
Studies from the United States Census Bureau and the American Medical Association concluded that learning among young school children...
Read More
High atop Mount Hollywood in Los Angeles, California, Griffith Observatory reopening in early November of 2006 after being closed and under...
Read More
From the outside there is no doubt that the Walt Disney Concert Hall is one of the most impressive architectural feats of the last century...
Read More